C&W News (2014)

SEPTEMBER 2014

MARINE GROWTH REMOVAL ON PLATFORM EUREKA

Eureka, CA

Illustration: Platform Eureka

 

Illustration: Diver entering water

 

Illustration: Diver inspecting platform risers

 

 

SCOPE OF WORK

Perform underwater marine growth. Inspect platform and report anomalies; CP anode/jackets/risers/sumps/landings/etc. cleaning and inspection; pipe pigging; and report development.

 

REQUIREMENTS

C&W performed marine growth removal operations and cathodic protection system anode inspection on platform Eureka. Divers cleaned all areas as required in project scope using 10K hydro blasting equipment. This was done within the predetermined time frame laid out in the project contract with crews working 12 hour days seven days per week till job scope was met.

 

LOCATION: Beta Complex, Offshore Southern California

PERFORMANCE PERIOD: 3 weeks

 