C&W News (2005)

NOVEMBER 2005 - DECEMBER 2005

CHARGER VESSEL RECOVERY 

Santa Rosa Island, CA

 

SCOPE OF WORK

C&W Diving was tasked with the debris removal and underwater salvaging of a 60 ft. vessel off Santa Rosa Island. All debris was placed on a barge and transported to Ventura.

 

POINT OF CONTACT:

AMS/SMS

Hans J. Anderson

(805) 452-7013

 

NOVEMBER 2005

AIRCRAFT RECOVERY

Dana Point, CA

 

SCOPE OF WORK

Within 24 hours of being contacted, C&W had staged and mobilized a DSV (Dive Support Vessel) to the Dana Point crash site, located approximately three miles offshore. The DSV was equipped with a crane, decompression chambers, and a mixed-gas fly-away dive system for the recovery operations. C&W divers located and recovered the aircraft in 210 feet of seawater and successfully transported it to land.

 

POINT OF CONTACT:

Aircraft Recovery Service

Jerry Prince

(661) 212-3996

 

FEBRUARY 2005

OLIVENHAIN DAM INTAKE SCREEN INSPECTION

San Diego County, CA

 

2005

 

SCOPE OF WORK

C&W inspected and adjusted the alignment mechanism on one of Olivenhain Dam's intake screens. In May 2006, C&W returned to the Fish Screen #1 Intake and repaired the alignment and guide shoes necessary for the traveling of the fish screen.

 

POINT OF CONTACT:

Kiewit Pacific

Melissa Meese

(928) 782-2235

 

JULY 2005 - OCTOBER 2005

DIVING SERVICES AT THE SAN ELIJO OCEAN OUTFALL

Cardiff-By-The-Sea, CA

 

SCOPE OF WORK

C&W completed pre-construction survey of the San Elijo Water Treatment Plant outfall pipe, which runs on the ocean floor for about 8,000' away from the shore. After it was determined that existing zinc anodes attached to the pipe were extremely deteriorated, C&W replaced them with new ones at eight separate stations underwater. C&W performed the tasks of an independent underwater inspector for Kennedy / Jenks during the full course of pipe reballasting work in the fall of 2005.

 

POINT OF CONTACT:

Kennedy / Jenks Consultants

Patrick Huston

(858) 676-3620

 

JUNE 2005 -  AUGUST 2005

DIVING SERVICES AT GREEN MOUNTAIN DAM AND POWER PLANT - PHASES I & II

Kremmling, CO

 

2005

 

SCOPE OF WORK

In June, 2005 C&W mobilized on-site and set up a marine work platform from which hoisting and dive operations were conducted. C&W utilized its ROV to verify positioning and preliminary inspection of a 21' diameter, 52,000 lb. bulkhead gate and related components. Divers cleaned and inspected affected vent lines on the bulkhead gate and determined that no repairs were necessary. Air dives to depths of 140' at an altitude of 8000' were performed. The bulkhead gate sealing surfaces were also cleaned and inspected. The bulkhead gate was removed from the stored position and lowered onto the vertical shaft. C&W returned in August 2005 to raise the bulkhead back into the storage position after all interior repairs were complete. C&W will return in 2006 for phase III of this project.

 

POINT OF CONTACT:

US Bureau of Reclamation, Billings, MO

Gerri Voto, Contracting Officer

(406) 247-7809

 

MAY 2005 - OCTOBER 2005

HUFF DRY DOCK DISPOSAL

San Pedro, CA

 

2005

 

SCOPE OF WORK

This project included complete planning, engineering analysis, management, and labor in safely removing a 540' by 130' dry dock structure from the Southwest Marine facility in San Pedro, CA. The structure was towed 12 miles offshore and safely sunk at the designated location utilizing USN and Coast Guard deep water scrapping techniques. Careful analysis and planning were utilized to devise the most economic and the least time consuming method of completing this task.

 

POINT OF CONTACT:

Southwest Marine

Robert Kilpatrick, President

(619) 238-1000 ext. 2810

 

JANUARY 2005 - JULY 2005

SAN DIEGO BAY FENDER PILE REPLACEMENT

San Diego, CA

 

SCOPE OF WORK

C&W performed various marine fendering and construction activities on this project as the prime contractor. C&W removed 80 plus timber piles and replaced with HDPE plastic piles. Original contract included modifications to and replacing existing pier fendering components including chocks and wales. Additional work awarded to C&W included installation of port security barriers, bank stability and seawall revetment, concrete removal, replacement of aids to navigation pile structures inside the San Diego Harbor and additional plastic pile installation.

 

POINT OF CONTACT:

San Diego Unified Port District

Mr. Marc Uribe, Project Manager

(619) 400-4713

 

SEPTEMBER 2004 - JANUARY 2005

DIAMOND VALLEY LAKE E MARINA PHASE II BOAT RAMP EXT

Hemet, CA

 

SCOPE OF WORK

As a prime contractor, C&W Diving Services extended the existing precast concrete boat ramp. The underwater portion consisted of salvage and reinstallation of 260 existing precast panels, salvage and reinstallation of boarding float system. Work also consisted of: establishing control and grade points, bottom profiling, excavating the reservoir bottom to subgrade, geotextile installation, beam installation, backfilling, compaction, panel placement and sealing. Above water portions included extending the V groove cast in place section of the boat ramp by 45,000 sq. ft. and constructing an additional 250 LF of rock slope protection and V-Ditch. All work was performed while maintaining public access.

 

POINT OF CONTACT:

Metropolitan Water District of Southern California

Carl Allen, Resident Engineer

(714) 577-5049

C&W NEWS